Case 04 · Industrial engineering · Automotive
One platform to plan engineers, hours, capacity and budgets across the projects that build automotive factories.
01
The problem
About the client
The client designs and builds complete automotive production facilities: assembly lines, robotics, body-in-white and battery production systems. Each project pulls in mechanical, electrical, software, PLC, robotics, simulation, project management and commissioning teams — and a delay in one discipline holds up the next.
Planning ran on fragmented information, manual coordination and disconnected tools. Project managers couldn't see who was free, who was overbooked, how planned hours compared with actual hours, or whether a budget was drifting — until it was late.
The result
02
The solution
We designed and developed a central engineering resource planning and workforce management platform. It brings availability, competencies, schedules, hours and finances into one system — so project managers, department heads and leadership share one view of current and future engineering work.
Profiles, disciplines, competencies, qualifications, availability and assignments.
Allocations that respect availability, skills, priorities and task dependencies.
Estimated, budgeted, scheduled, actual and remaining engineering hours.
Supply against demand by person, team, department and period.
Planned vs actual cost, cost-to-complete, variance and profitability.
Milestones, dependencies and the knock-on effect of every change.
The right KPIs for each level, from team lead to leadership.
03
Implementation
Each business domain — employees, projects, allocation, scheduling, time tracking, capacity, finance and reporting — is its own component, so each can evolve independently.
Illustrative example · catching overbooking
One engineer, 40 contracted hours a week, booked on three projects:
Planned
52h
Utilisation
130%
Conflict
12h
The platform flags the conflict so managers can rebalance the work before it affects delivery.
When one allocation changes, the platform recalculates only the affected people, projects and periods. Heavier calculations run in the background, while database-level filtering, indexing and aggregation keep queries over large planning datasets fast.
Stack
04
What went wrong
Issue
We underestimated the scheduling rules. Part-time staff, absences, international calendars, shifting priorities and task dependencies meant a choice that looked fine for one person could clash at project or department level.
Fix
A scheduling engine designed around real-world constraints and built up together with the business — flexible without becoming needlessly complex.
Issue
Moving one milestone by two weeks could ripple through assignments, department capacity, other projects and the finances.
Fix
Calculation separated from transactions: only affected entities and periods are recalculated, with expensive work running asynchronously.
Issue
Project managers, department heads, finance and leadership each meant something different by “capacity” and “utilisation”.
Fix
Shared definitions and calculation rules, validated continuously with stakeholders, so every view comes from the same model.
Issue
Schedules, reported hours and finances change independently — often at the same time, by different people.
Fix
Clear transaction boundaries, conflict handling and consistent recalculation of derived values.
05
Finalisation
Engineering360 became the central place to plan and track engineering work, so shortages, overbooking and budget drift show up while there's still time to act.
Illustrative financial impact
Illustrative scenario. Figures show equivalent engineering capacity, not direct cash savings.
Impact
Lessons learned