All work

Case 04 · Industrial engineering · Automotive

Engineering360

One platform to plan engineers, hours, capacity and budgets across the projects that build automotive factories.

Client
Leading German industrial engineering & automotive manufacturing solutions group
Industry
Automotive manufacturing, robotics, Industry 4.0
Duration
12 months
Confidentiality
Project name, client name and client data are anonymised. Client figures are rounded.
12 monthsfrom fragmented planning tools to one platform
7connected modules
8engineering disciplines planned together

01

The problem

Every delay ripples downstream.

About the client

2,000+employees worldwide
€500M+annual revenue
~1,000industrial robots integrated a year
100,000+engineering hours a year

The client designs and builds complete automotive production facilities: assembly lines, robotics, body-in-white and battery production systems. Each project pulls in mechanical, electrical, software, PLC, robotics, simulation, project management and commissioning teams — and a delay in one discipline holds up the next.

Planning ran on fragmented information, manual coordination and disconnected tools. Project managers couldn't see who was free, who was overbooked, how planned hours compared with actual hours, or whether a budget was drifting — until it was late.

The result

  • Overbooked engineers and scheduling conflicts
  • Unused capacity in other departments
  • Little view of future workforce needs
  • Budget overruns spotted late
  • Heavy manual planning and reporting
  • Risk of missing contractual deadlines

02

The solution

One view of people, time and money.

We designed and developed a central engineering resource planning and workforce management platform. It brings availability, competencies, schedules, hours and finances into one system — so project managers, department heads and leadership share one view of current and future engineering work.

M1

Resource management

Profiles, disciplines, competencies, qualifications, availability and assignments.

M2

Workforce scheduling

Allocations that respect availability, skills, priorities and task dependencies.

M3

Hours tracking

Estimated, budgeted, scheduled, actual and remaining engineering hours.

M4

Capacity planning

Supply against demand by person, team, department and period.

M5

Financial planning

Planned vs actual cost, cost-to-complete, variance and profitability.

M6

Dependency management

Milestones, dependencies and the knock-on effect of every change.

M7

Reporting & analytics

The right KPIs for each level, from team lead to leadership.

03

Implementation

Catching problems while they're still fixable.

Each business domain — employees, projects, allocation, scheduling, time tracking, capacity, finance and reporting — is its own component, so each can evolve independently.

Illustrative example · catching overbooking

One engineer, 40 contracted hours a week, booked on three projects:

A · 24h
B · 12h
C · 16h
40h capacity

Planned

52h

Utilisation

130%

Conflict

12h

The platform flags the conflict so managers can rebalance the work before it affects delivery.

When one allocation changes, the platform recalculates only the affected people, projects and periods. Heavier calculations run in the background, while database-level filtering, indexing and aggregation keep queries over large planning datasets fast.

Stack

C#.NETASP.NET Core Web APIEntity Framework CoreSQLDomain-driven designBackground servicesRole-based accessCI/CD

04

What went wrong

Scheduling is a business problem, not a calendar.

Issue

We underestimated the scheduling rules. Part-time staff, absences, international calendars, shifting priorities and task dependencies meant a choice that looked fine for one person could clash at project or department level.

Fix

A scheduling engine designed around real-world constraints and built up together with the business — flexible without becoming needlessly complex.

Issue

Moving one milestone by two weeks could ripple through assignments, department capacity, other projects and the finances.

Fix

Calculation separated from transactions: only affected entities and periods are recalculated, with expensive work running asynchronously.

Issue

Project managers, department heads, finance and leadership each meant something different by “capacity” and “utilisation”.

Fix

Shared definitions and calculation rules, validated continuously with stakeholders, so every view comes from the same model.

Issue

Schedules, reported hours and finances change independently — often at the same time, by different people.

Fix

Clear transaction boundaries, conflict handling and consistent recalculation of derived values.

05

Finalisation

How it landed.

Engineering360 became the central place to plan and track engineering work, so shortages, overbooking and budget drift show up while there's still time to act.

Illustrative financial impact

€72Myearly engineering cost: 500 engineers × 1,800 hours × €80
€1.44Mof capacity from a 2% utilisation gain (18,000 hours)
€3.6Mof capacity from a 5% gain (45,000 hours)

Illustrative scenario. Figures show equivalent engineering capacity, not direct cash savings.

Impact

  • Clear view of engineering capacity
  • Earlier warning of resource shortages
  • Less overbooking and manual coordination
  • Earlier sight of potential budget overruns
  • Better coordination between departments
  • Clearer view of costs and profitability
  • Better-informed hiring and outsourcing decisions

Lessons learned

  1. 01Enterprise scheduling is a business-domain problem, not a calendar.
  2. 02Capacity, utilisation and finance are tightly linked.
  3. 03Define business rules explicitly — and validate them with stakeholders.
  4. 04Large-scale planning needs incremental calculation.
  5. 05Good software supports decisions ahead of time, not just reports on the past.